Skip to content
menu (1)
cross
Back

The Hidden Strain: Why Weather Contract Claims in Construction Are Getting Harder — What You Can Do About It

Weather is one of the most common and costly causes of delay in construction — yet ironically, it’s also one of the hardest to get compensated for.

Despite a global uptick in extreme weather events, most contractors are still navigating contractual frameworks, evidentiary standards, and scheduling systems that were never designed for today’s climate realities. The result? Valid weather impacts are frequently under-claimed, contested, or rejected altogether.

This article outlines the core barriers to successful weather claims — and what’s changing in the way forward-thinking contractors are managing this risk.

nicolas-houdayer-7A9mqiLfFWQ-unsplash

1. The Contractual Catch: You May Not Be Entitled to Relief

Weather risk is not uniformly addressed in construction contracts. In fact, it’s often explicitly assigned to the contractor — even for unforeseeable events.

  • Under JCT contracts, there may be an entitlement to an extension of time for “exceptionally adverse weather conditions” — but that term is undefined and open to dispute.

  • Under the FIDIC Silver Book, typically used in EPC and turnkey projects, no weather-related relief is provided at all.

  • Under NEC contracts, early warnings and compensation events require proactive notification and are strictly time-bound.

Without clear wording, contractors are often left absorbing delays, costs, and disputes — even when weather clearly contributed.

 

2. Proving “Exceptional” Weather Is Increasingly Difficult

With climate extremes becoming more common, the evidentiary bar for “exceptional” weather is rising.

A contractor must show:

  • The event exceeded long-term averages or defined thresholds.

  • The event was not reasonably foreseeable based on location and time of year.

  • The weather was materially different from what could have been planned for.

Relying on regional weather station data or generic reports often falls short. Site-specific impacts — like wind speed at crane height — are rarely captured without proactive monitoring.

 

3. Evidence Must Be Contemporaneous, Granular, and Verifiable

To substantiate a weather claim, a contractor typically needs:

  • Localised historical and real-time weather data

  • Daily site diaries referencing specific impacted activities

  • Photographic/video evidence timestamped to the event

  • Schedule overlays that trace delays to critical path activities

The use of forecasts or summary statements alone is insufficient. Claims lacking robust, contemporaneous records are often dismissed — even if the disruption was obvious on site.

remi-jacquaint-uwdJRCtgLRI-unsplash

4. It’s Not Enough to Show Weather — You Must Show Delay to the Critical Path

Delays are only compensable if they directly impact the critical path. This means:

  • An activity must be weather-sensitive

  • It must be on the critical path at the time of disruption

  • The weather must have caused a delay to project completion, not just activity progress

Many contractors struggle to draw this link clearly in their documentation, especially without integrated schedule analysis tools.

 

5. Most Weather Claims Are Time-Only — Not Cost-Based

Even when successful, most claims only provide extensions of time — not financial compensation. To recover costs, contractors must often:

  • Demonstrate the event was not only adverse, but also compensable under the contract

  • Show resulting cost impacts were unavoidable and quantifiable

This threshold is difficult to meet, especially when poor documentation or delayed notices weaken the claim.

 

6. Timing and Process Are Just As Important as Evidence

Late or irregular claims are easy to reject. Many standard forms require notice within days of becoming aware of a delay — and ongoing evidence collection throughout the project.

Failing to:

  • Raise early warnings

  • Submit claims on a rolling basis

  • Track actual weather impacts as they occur can undermine an otherwise valid entitlement.

 

What This Means in Practice

Even with good intentions, contractors face a minefield of technical, procedural, and evidentiary hurdles:

Challenge

What’s Required

Contractual Entitlement

Clause-based rights to time or money for weather

Threshold Definition

Proof that weather was abnormal based on site-specific historical norms

Evidence Quality

Precise, real-time site records linked to activity impacts

Critical Path Proof

Schedule analysis showing delay to project completion

Timing and Notices

Early warnings and contemporaneous claims process

Compensation Basis

Distinction between excusable (time-only) and compensable (cost + time)

matt-hardy-55NI4yEAas4-unsplash

So What Can Be Done?

Weather risk is rising. Claims are getting harder. But better planning and smarter data are making a difference.

Contractors who embed site-specific thresholds, automate their recordkeeping, and link weather directly to schedules are seeing far greater success — even in adversarial contract environments.

At EHAB, we’re helping contractors do exactly that — not through a new tool to buy, but through targeted support.

If you’re struggling to:

  • Understand your entitlements under NEC, JCT, or FIDIC

  • Retrospectively assess whether weather delayed your critical path

  • Improve your evidence trail to support better negotiation

 

Then we’re happy to talk.

 

If weather delays are impacting your projects — and your ability to prove them — we’re here to help.

 

We’re currently providing consultation and support to contractors who want to strengthen their claims, identify missed compensation opportunities, or just get a second opinion on the risk they’re carrying.

 

👉 If that’s relevant to you, reach out here— no sales pitch, just a conversation.

Enjoying these articles?

Subscribe to our newsletter to get more just like it, sent straight to your inbox.

By subscribing, you consent for EHAB to store your details and email you our newsletter, product features and latest news. You can unsubscribe at any time. Privacy policy.